Hot Topics » Norman ES Project Schedule

Norman ES Project Schedule

HUTTO INDEPENDENT SCHOOL DISTRICT

 

DATE: 09.23.2014

PROJECT SCHEDULE

2014

 

September - October 23

Owner/Architect Meetings with stakeholders to verify design

October 9

Director of Facilities presents to school board meeting to bring everyone up to date on the progress of the design

October 9

Consultant Coordination re-Kick-off Meeting

October 23

Consultant Coordination Meeting

November 6

Consultant Coordination Meeting

November 13

Director of Facilities presents to school board meeting to update design progress

November 20

 

95% CD Documents & Consultant Coordination Meeting

    Send pdfs of plans to Architect by December 3

    Bring one updated table of contents AND all specification sections

Redlines plan will be issued after the meeting

 

November 21 – December 5

 

Quality control check by Owner, Contractor, Architect and all Consultants

December 8 - December 16

Design Team incorporates all changes, finalizes drawings and specs.

December 11

Director of Facilities presents Construction Documents of Elementary School #6 to Board of Trustees for review. School Board authorizes the Construction Manager to send out plans for proposals.

December 17

100% Contract Documents due at Architects office by Noon. pdf of plans and specifications, sealed and signed.

 

December 18 - December 19

 

Drawings and specs are issued, sent out to design team, Owner, TAS, City of Hutto and Bidders.

2015

 

 

December 19 - January 29

 

Bidding & Permitting

 

January 29

 

Bid Date

 

January 30 –

 

Construction Manager to review proposals


 

ContactThomas Bloxham(512) 759-3771thomas.bloxham@hutto.txed.net

March 12

 

 

March 12

(or next available

Board Meeting)

 

Director of Facilities presents proposals for Norman Elementary School to Board of Trustees for review. School Board authorizes the Construction Manager to proceed with construction.

 

April